Work is entered in
Supported on: At least Windows Server 2008 R2 or Windows 7
Registry
HKCU
software\policies\microsoft\office\16.0\ms project\options\scheduling Options
default work units enum - Minutes
->
3 - Hours
->
5 - Days
->
7 - Weeks
->
9 - Months
->
11
Description
Specifies the default unit of time (minutes, hours, days, weeks, or months) used in the Work field in the current project. If you enable this setting, whenever Project displays work values, the unit you specified will be used. If you disable or do not configure this setting, the user's default setting is used.