Split in-progress tasks
Supported on: At least Windows Server 2008 R2 or Windows 7
Registry
HKCU
software\policies\microsoft\office\16.0\ms project\options\scheduling Value name: auto split tasks
Enabled: auto split tasks = 1
Disabled: auto split tasks = 0
Description
Allows rescheduling of remaining duration and work when a task slips or reports progress ahead of schedule. If you enable this setting, the remaining duration and work will be rescheduled if a task slips or reports progress ahead of schedule. If you disable or do not configure this setting, the user's default setting is used.