Show that tasks have estimated durations

Supported on: At least Windows Server 2008 R2 or Windows 7

Registry

HKCU software\policies\microsoft\office\16.0\ms project\options\scheduling

Value name: show estimated durations

Enabled: show estimated durations = 1

Disabled: show estimated durations = 0

Description

Displays a question mark (?) after the duration unit of any task with an estimated duration. If you enable this setting, tasks with estimated durations have a question mark after their duration unit. If you disable or do not configure this setting, the user's default setting is used.