en-US

Inserted projects are calculated like summary tasks

Supported on: At least Windows Server 2008 R2 or Windows 7

Registry

HKCU software\policies\microsoft\office\16.0\ms project\options\calculation

Value name: inserted projects are calculated like summary tasks

Enabled: inserted projects are calculated like summary tasks = 1

Disabled: inserted projects are calculated like summary tasks = 0

Description

Specifies that a single critical path is calculated throughout the master project, by treating inserted projects as summary tasks in the master project. If you enable this setting, the critical path is calculated by treating inserted projects as summary tasks. If you disable or do not configure this setting, the user's default setting is used.